Several issues are revealed in this forum, especially those which are related to the Palapa Ring Project:
- The RFP is delayed possibly till the 3rd week of march.
- The consortium will build 3 rings connecting 32 places in eastern Indonesia. However the topology differs than that originally proposed by TT-Tel (compare two pics on the right! - the above pic is an artwork -- not official!)
- Length : 9,350 km undersea; 1,860 km inland
- CAPEX : approx. USD 260 mn
- Cable : 2 FP (undersea with repeater - 16/2.5 or 16/10?); 12 FP (inland / undersea repeaterless)
- Capacity : 9 lambdas lit (either 20 Gbps or 90 Gbps?), 16 potential;
- Capacity/Company : Telkom/4 , Indosat/1, BTEL/1, XL/1, Powertek/1, Infokom/0.44
- RFS : late 2009 / early 2010