Below are several issues related to the project as of March 2008 (source KOMINFO - Ministry of Information and Communications) :
- Capacity 10 Lambdas @ 10 Gbps upgradeable to 16 Lambdas (updated - see my previous PR post)
- Length of the cable 11,202 km (1,857 km inland, 9,345 km submarine)
- Construction begin on Jan 2009; RFS final (all segments) on April 2010
- Section Mataram - Parigi shall be ready (RFS) on Q1/2009
- Section Palu-Manado-Makassar-Kendari RFS on Q2/2009
- Section Kendari-Sorong-Ende-Makassar RFS on Q4/2009
- Section Sorong-Jayapura-Fakfak-Merauke RFS on Q1/2010
- General Palapa Ring project description from KKPPI (click here for a local copy)
- Request for Pre-Qualification from the consortium; searchable from Indosat's or Infokom's sites (click here for a local copy); a different version can be access via the DGPT site
- From the DGPT site you may also see the preliminary Palapa Ring network map (click here for a local copy)
No comments:
Post a Comment